*By Jules Rogers*

A turbulent wind storm in the early hours of September 25 left the City of Canby in the dark after an unexpected electrical failure knocked out a vital power hub.

At approximately 1:40 p.m. Friday, an external transmission line feeding the Westcott Substation abruptly tripped offline, severing electricity across the area. While utility crews managed to re-energize the incoming transmission line by 3:00 p.m., the storm's aftermath revealed deeper damage inside the substation: a compromised transformer.

“We do not know the specific cause of the outage from last Friday,” said Kari Duncan, general manager of Canby Utility.

Technicians inspecting the equipment traced the failure directly to a damaged lightning arrester, which is the critical shield designed to protect heavy grid infrastructure from high-voltage electrical surges.

To bring homes and businesses back online quickly, Canby Utility crews isolated the damaged unit, safely routing power through an alternate transformer. By roughly 6:00 p.m. Friday, lights flickered back on across the city.

Repair crews worked through the weekend to replace the faulty hardware, officially returning the primary transformer to service the following day. 

“We do want to give a big thank you to the City of Canby, Canby Fire, and PGE for supporting us and the community while our staff worked on the outage,” Duncan said.